Sector
Technology & Service Industry
Location
Uptown Dubai District
Status
Completed
Client
DMCC
Architect / Location
BSBG
Main Contractor
DBB CONTRACTING LLC
The Challenge
DMCC Uptown Phase 2 needed to protect its atrium despite a complex ceiling geometry, while achieving life and safety compartmentation and integration with the building's Fire Alarm (FA) system.
The Dosteen Solution
Provided Concertina Fire Master Fire Curtain that meets the area shape and the Life and Safety product it requires.
Systems & Products
Systems Name Concertina "Open" FireMaster Fire Curtain
Brand / PartnerCoopers Fire Limited
Application on ProjectPodium Lift Lobby
Quantity / Scale2 nos.
Key Specification078700
Why SelectedIt meets the Client requirement to close the Lift Lobby with a Fire Curtain at the event of Fire
The Outcome
Dosteen supplied a Concertina "Open" Fire Master Fire Curtain (2 nos.) at the Podium Lift Lobby, designed to accommodate the complex ceiling geometry while integrating with the building's life and safety requirements. The system successfully achieved the required fire-resistance performance, operational reliability, and integration requirements — delivering effective fire compartmentation, compliance with fire and life safety requirements, and enhanced occupant safety and asset protection despite the complex design.